Summary of upcoming key dates

Work begins 26th September

Scaffold erection on west elevation 26th September

Works to disconnect existing gas and electricity supplies for 2 weeks

Works will be carried out by Cadent Gas & UKPN

An application for the closure of Cuba St has been made for the duration of these works

Scaffold and hoarding erection on Marsh Wall with footpath width reduced to facilitate
3rd October

Scaffold and hoarding erection on Cuba St with footpath closed for duration of the project 10th October

Demolition begins 17th October