Work begins
26th September
Scaffold erection on west elevation
26th September
Works to disconnect existing gas and electricity supplies for 2 weeks
Works will be carried out by Cadent Gas & UKPN
An application for the closure of Cuba St has been made for the duration of these works
Scaffold and hoarding erection on Marsh Wall with footpath width reduced to facilitate 3rd October
Works will be carried out by Cadent Gas & UKPN
An application for the closure of Cuba St has been made for the duration of these works
Scaffold and hoarding erection on Marsh Wall with footpath width reduced to facilitate 3rd October
Scaffold and hoarding erection on Cuba St with footpath closed for duration of the project
10th October
Demolition begins
17th October